On October 22, 2024, from 9:00 am to 11:00 am, Atlantic Richfield, EPA, Butte Silver Bow County, Montana DEQ, and the Montana Natural Resource Damage Program invite the public to observe the Butte Priority Soils Operable Unit (BPSOU) Remedial Design/Remedial Action Progress Meeting (RDRA Progress Meeting) in a Teams event by computer or smart phone. Because you will be watching a working meeting, there will be no method for asking questions or making statements.
General:
- Introduction and Expectations (Mike)
- Safety Moment (Jacobs)
Construction:
- Lexington Wetlands (Kevin/Randy)
- Restroom
- Boardwalk
- Remaining Sidewalks
- Furnishings
- Paving
- Lighting
- Grove Gulch (Kevin/Randy)
- Site Backfill and Grading
- Grove Creek Channel
- Helical Piers
- Concrete Work
- Winterization
Pre-Mobilization:
- BRW Phase II D&D
- D&D Plan Update
- Bid Schedule
- Casey Street Water Line (Kevin/Randy)
- Railroad ROW Encroachment and Casing
- Plan Finalization
Design and Investigation:
- Buffalo Gulch (Gil/Scott/Emily)
- Diggings East (Joe/Ross)
- Northside Tailings (Karen)
- BPSOU Pump Station (Karen)
- Butte Reduction Works (Karen)
- Geotechnical Investigation
- General Update
- Groundwater Remedy Optimization (Brent/Karen)
- Site-Wide Model
- Infiltration Evaluation and Leak Detection
- BPSOU Pump Station
- BTC Hydraulic Control (Brent)
- PDIWP/PDIER
- 30% Design Submittal
- Blacktail Creek Riparian Actions (Logan/Daryl)
- Copper Mountain (Emily)
Planning:
- SBCCA Program Plans (Tim/Josh)
- Technical Specifications
- CQAP/CMQAPP
- Materials Management Plan
- OM&M Plan
- Greener Clean-Ups
- Repository (Josh)
- Materials Management Plan
- RSS Technical Evaluations and Recommendations Report
- Investigation Activities
Other:
- Restoration Activities
- Community Engagement
- Round Table
________________________________________________________________________________