Atlantic Richfield will continue demolition at Butte Reduction Works (BRW) to support remediation of BRW and subsequent construction of the Silver Bow Creek Conservation Area. Construction crews will demolish segments of the slag wall immediately adjacent to Montana...
Search BPSOU
Remedial Activities at Belle of Butte Site
Beginning in late November of 2024, reclamation will begin at the Belle of Butte site. The Belle of Butte site is located in Walkerville on North Main and East Clark Streets. Dunn Street and East Clark Street Park Closure Signs
BPSOU RD/RA Progress Meeting
The next Butte Priority Soils Operable Unit (BPSOU) Remedial Design/Remedial Action (RD/RA) Meeting will be held on Tuesday, November 7th, 2023, from 9:00 to 11:00 A.M. Click to Join Nov 7 RD/RA Progress Meeting. Technical issues that occurred during the last meeting are being diligently worked on to be resolved for this upcoming meeting. Executive summaries of these meetings will be posted on the EPA website.
Future BPSOU RD/RA Meetings will be posted on the bpsou.com Calendar of Events, found here: https://bpsou.com/events/.